Colorado State University Project Management Schedule Chart Analysis
Download and examine the project task list from the link provided in the module. Based on this task list, you will create a PERT chart and write a paper that discusses the following:
- Identify which set of tasks create the critical path.
- Determine which task would be best to crash to reduce the critical path.
- Determine if there is a change to the critical path by crashing the task. Is there a new critical path?
- What other information would be beneficial to know to see if the selected task was the best option for crashing?